The table below provides a summary of the additional resurfacing work the Council is delivering.
Date | Area work is planned | Type of work | Cost | Area m2 | Benefits |
---|---|---|---|---|---|
TBC | Craster Road (Chirton) | Resurfacing | £31,676.82 | 571 | Improved road surface on full length |
TBC | Chiltern Road (Collingwood) | Resurfacing | £19,844.50 | 858 | Improved road surface from outside no.14. to no.22. (half road width) & outside no.22. to corner of no.33. (full road width) |
TBC | Farringdon Road (Cullercoats) | Resurfacing | £16,012.50 | 607 | Improved road surface from opposite no.102. to outside no.97. |
TBC | Kielder Road (St Mary's) | Resurfacing | £37,101.58 | 697 | Improved road surface from the junction of Kielder Place/Houxty Road to junction of Otterburn Avenue |
TBC | Park Lane (Valley) | Resurfacing | £110,509.76 | 2742 | Improved road surface from outside no.2. to just past junction of Lesbury Avenue |
TBC | Rotary Road (Valley) | Resurfacing | £97,068.33 | 4222 | Improved road surface on two sections of dual carriageway (plans available) |
TBC | Edith Street (Tynemouth) | Resurfacing | £21,933.94 1 | 1042 | 2 Improved road surface on full length |
TBC | Algernon Terrace (Tynemouth) | Resurfacing | £5,934.45 | 269 | Improved road surface from side of 1 Algernon Terrace to side of 48 Edith Street |
TBC | Addington Drive (Battle Hill) | Resurfacing | £36,100.01 | 760 | Improved road surface at Bewick Park Roundabout |