Additional Department for Transport funding

In November 2023, the Department for Transport published details of £8.3 billion in extra funding for local road resurfacing. £3.3 billion was allocated for the North of England.

The funding is part of the Network North plan to improve journeys for all. It provides long-term certainty to local authorities.

We received funding, unlocked from the government’s Network North Plan, for additional resurfacing in 2023/24 and 2024/25.

The table below provides a summary of the additional resurfacing work the Council is delivering.

2023/24 Areas / roads where work is planned Type of works being undertaken on asset group (eg: road resurfacing, bridge repair, culverts maintenance, cycleways, footways etc) Indicative cost Surface area resurfaced (if applicable) m2  Benefits from it (eg: improved journey times etc)
Complete Killingworth Way (Camperdown) Resurfacing £83,460.08 3289 Improved road surface on roundabout and its junctions
Complete Verne Road (Chirton) Patching £31,643.80 362 Improved road safety by removing and replacing 5 no. sets of speed cushions
Complete Malvern Road (Collingwood) Patching £5,256.35 75 Improved road surface 1 no. patch close to no.24. Malvern Road (to the front of garage area)
Complete The Broadway (Cullercoats) Resurfacing £34,203.66 1044 Improved road surfaced from outside no.325. The Broadway up to and including Mast Lane roundabout
Complete Churchill Street (Howdon) Resurfacing £18,690.24 618 Improved road surface from outside no.280. to outside no.298.
Complete Tynemouth Road (Howdon) Patching £16,913.16 215 Improved road surface 5 no. patches in the vicinity of Bewicke Lodge and Bewicke Medical Centre
Complete Coronation Street (Wallsend) Resurfacing £40,936.38 1689 Improved road surface on full length
Complete Durham Street West (Wallsend) Resurfacing £8,711.59 363 Improved road surface from the junction of Coronation Street to the junction of Ferndale Avenue
Complete Stalks Road (Weetslade) Resurfacing £70,831.75 2641 Improved road surface from the junction with Rayleigh Drive in Wideopen to near the Bradbury Centre in Brunswick Village
Complete Various Locations Coring £27,695.60 N/A Core samples for the 2024/25 resurfacing programme
2024/25 Areas / roads where work is planned Type of works being undertaken on asset group (eg: road resurfacing, bridge repair, culverts maintenance, cycleways, footways etc) Indicative cost Surface area resurfaced (if applicable) m2  Benefits from it (eg: improved journey times etc)
Complete Craster Road (Chirton) Resurfacing £31,676.82 571 Improved road surface on full length 
Complete Chiltern Road (Collingwood) Resurfacing £19,844.50 858 Improved road surface from outside no.14. to no.22. (half road width) & outside no.22. to corner of no.33. (full road width)
Complete Farringdon Road (Cullercoats) Resurfacing £16,012.50 607 Improved road surface from opposite no.102. to outside no.97.     
Complete Kielder Road (St Mary's) Resurfacing £37,101.58 697 Improved road surface from the junction of Kielder Place/Houxty Road to junction of Otterburn Avenue
Complete Park Lane (Valley) Resurfacing £110,509.76 2742 Improved road surface from outside no.2. to just past junction of Lesbury Avenue
Complete Rotary Road (Valley) Resurfacing £97,068.33 4222 Improved road surface on two sections of dual carriageway (plans available)
Complete Edith Street (Tynemouth) Resurfacing £21,933.94 1042 Improved road surface on full length
Complete Algernon Terrace (Tynemouth) Resurfacing £5,934.45 269 Improved road surface from side of 1 Algernon Terrace to side of 48 Edith Street
Complete Addington Drive (Battle Hill) Resurfacing £36,100.01 760 Improved road surface at Bewick Park Roundabout

Full document available below