Network North Roads Resurfacing Fund - SmartSurvey Reporting Requirements

2023/24

2023/24 Areas/roads where work is planned Type of works being undertaken on asset group (eg: road resurfacing, bridge repair, culverts maintenance, cycleways, footways etc)
Complete Killingworth Way (Camperdown) Resurfacing
Complete Verne Road (Chirton) Patching
Complete Malvern Road (Collingwood) Patching
Complete The Broadway Resurfacing
Complete Tynemouth road (Howdon) Patching
Complete Coronation Street (Wallsend) Resurfacing
Complete Durham Street West (Wallsend) Resurfacing
Complete Stalks Road (Weetslade) Resurfacing
Complete Various locations  Coring

2024/25

2023/24 Areas/roads where work is planned Type of works being undertaken on asset group (eg: road resurfacing, bridge repair, culverts maintenance, cycleways, footways etc)
Complete Craster Road (Chirton) Resurfacing
Complete Chiltern Road (Collingwood) Resurfacing
Complete Farringdon Road (Cullercoats) Resurfacing
Complete Kielder Road (St Mary's) Resurfacing
Complete Park Lane (Valley) Resurfacing
Complete Rotary Road (Valley) Resurfacing
Complete Edith Street (Tynemouth) Resurfacing
Complete Algernon Terrace (Tynemouth) Resurfacing
Complete Addington Drive (Battle Hill) Resurfacing

The plan should include summaries of the additional resurfacing and other work either completed in 2023/24 or scheduled in 2024/25 using the additional funding in Budget 2023 and the further funding confirmed in this letter. This should set out the total volumes of additional work already completed and due to be completed by March 2025; particular roads, communities, or locations that have already benefited from it, or that are due to benefit from it; and the further additional work that will be completed during 2024/25 – again setting out both expected total volumes of additional work and where it is planned.

Indicative cost Surface area resurfaced (if applicable) m2 Benefits from it (eg: improved journey times etc)
£83,460.08 3289 Improved road surface on roundabout and its junctions
£31,643.80 362 Improved road safety by removing and replacing 5 no. sets of speed cushions
£5,256.35 75 Improved road surface 1 no. patch close to no.24. Malvern Road (to the front of garage area)
£34,203.66 1044 Improved road surfaced from outside no.325. The Broadway up to and including Mast Lane roundabout
£18,690.24 618 Improved road surface from outside no.280. to outside no.298.
£16,913.16 215 Improved road surface 5 no. patches in the vicinity of Bewicke Lodge and Bewicke Medical Centre
£40,936.38 1689 Improved road surface on full length
£8,711.59 363 Improved road surface from the junction of Coronation Street to the junction of Ferndale Avenue
£70,831.75 2641 Improved road surface from the junction with Rayleigh Drive in Wideopen to near the Bradbury Centre in Brunswick Village
£27,695.60 N/A Core samples for the 2024/25 resurfacing programme
£31,676.82 571 Improved road surface on full length
£19,844.50 858 Improved road surface from outside no.14. to no.22. (half road width) & outside no.22. to corner of no.33. (full road width)
£16,012.50 607 Improved road surface from opposite no.102. to outside no.97.
£37,101.58 697 Improved road surface from the junction of Kielder Place/Houxty Road to junction of Otterburn Avenue
£110,509.76 2742 Improved road surface from outside no.2. to just past junction of Lesbury Avenue
£97,068.33 4222 Improved road surface on two sections of dual carriageway (plans available)
£21,933.94 1042 Improved road surface on full length
£5,934.45 269 Improved road surface from side of 1 Algernon Terrace to side of 48 Edith Street
£36,100.01 760 Improved road surface at Bewick Park Roundabout

The plan should include summaries of the additional resurfacing and other work either completed in 2023/24 or scheduled in 2024/25 using the additional funding in Budget 2023 and the further funding confirmed in this letter. This should set out the total volumes of additional work already completed and due to be completed by March 2025; particular roads, communities, or locations that have already benefited from it, or that are due to benefit from it; and the further additional work that will be completed during 2024/25 – again setting out both expected total volumes of additional work